PROGRESS REPORT |
CONSTRUCTION OF "KRISHNACHURA" OF AKANKHA PROJECT |
May-11 |
SL. No. |
Particulars |
Completion Date |
Tower-1 |
Tower-2 |
Tower-3 |
1 |
Foundation |
100% |
100% |
100% |
2 |
RCC 1st
Floor Slab |
100% |
100% |
100% |
3 |
RCC 2nd Floor Slab |
100% |
100% |
100% |
4 |
RCC 3rd
Floor Slab |
100% |
100% |
100% |
5 |
RCC 4th
Floor Slab |
100% |
100% |
100% |
6 |
RCC 5th Floor Slab |
100% |
100% |
100% |
7 |
RCC 6th
Floor Slab |
100% |
100% |
100% |
8 |
RCC 7th
Floor Slab |
100% |
100% |
100% |
9 |
RCC 8th Floor Slab |
100% |
100% |
100% |
10 |
RCC 9th
Floor Slab |
100% |
100% |
100% |
11 |
RCC 10th
Floor Slab |
100% |
100% |
100% |
12 |
RCC 11th Floor Slab |
100% |
100% |
100% |
13 |
RCC 12th
Floor Slab |
100% |
100% |
100% |
14 |
RCC 13th
Floor Slab |
100% |
100% |
100% |
15 |
RCC 14th Floor Slab |
100% |
100% |
100% |
16 |
RCC 15th
Floor Slab |
100% |
100% |
100% |
17 |
RCC 16th
Floor Slab |
100% |
100% |
100% |
18 |
RCC 17th Floor Slab |
100% |
100% |
100% |
19 |
RCC 18th
Floor Slab |
100% |
100% |
100% |
20 |
RCC 19th
Floor Slab |
100% |
100% |
100% |
21 |
RCC 20th Floor Slab |
100% |
100% |
100% |
22 |
RCC 21st
Floor Slab |
100% |
100% |
100% |
23 |
RCC 22nd
Floor Slab |
100% |
100% |
100% |
24 |
RCC 23rd Floor Slab |
100% |
100% |
100% |
25 |
Roof Slab |
100% |
100% |
100% |
26 |
Above Roof
Slab |
100% |
100% |
100% |
27 |
Brickwork 100% Upto |
100% |
100% |
100% |
28 |
Inside
Plaster 100% Upto |
100% |
100% |
100% |
29 |
Flooring
100% from 2nd to 6th Floor |
100% |
100% |
100% |
30 |
Flooring 100% from 7th to 13th Floor |
100% |
100% |
100% |
31 |
Flooring
100% from 14th to 15th Floor |
100% |
100% |
100% |
32 |
Flooring
100% from 16th to 23rd Floor |
100% |
100% |
100% |
33 |
DW Upto 15th Floor |
100% |
100% |
100% |
34 |
DW Upto
15th to 23rd Floor |
100% |
100% |
100% |
35 |
Plumbing
(Excluding Fittings) |
100% |
100% |
100% |
36 |
Electrification (Excluding Fittings) |
100% |
100% |
100% |
37 |
IF from
2nd to 6th Floor |
100% |
100% |
100% |
38 |
IF from
7th to 15th Floor |
100% |
100% |
100% |
39 |
IF from 16th to 23rd Floor |
100% |
100% |
100% |
40 |
Supply
& Erection of Lift |
100% |
100% |
100% |
41 |
Outside
Plaster Upto 6th Floor |
100% |
100% |
100% |
42 |
Outside Plaster from 7th to 13th Floor |
100% |
100% |
100% |
43 |
Outside
Plaster from 14th to 15th Floor |
100% |
100% |
100% |
44 |
Outside
Plaster 100% from 16th to 23rd Floor |
100% |
100% |
100% |
45 |
Outside Painting |
95% |
95% |
95% |
46 |
Ready to
Handover |
95% |
95% |
95% |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|