PROGRESS REPORT 
CONSTRUCTION OF "KRISHNACHURA" OF AKANKHA PROJECT May-11
SL. No. Particulars Completion Date  
Tower-1 Tower-2 Tower-3
1 Foundation 100% 100% 100%
2 RCC 1st Floor Slab 100% 100% 100%
3 RCC 2nd Floor Slab 100% 100% 100%
4 RCC 3rd Floor Slab 100% 100% 100%
5 RCC 4th Floor Slab 100% 100% 100%
6 RCC 5th Floor Slab 100% 100% 100%
7 RCC 6th Floor Slab 100% 100% 100%
8 RCC 7th Floor Slab 100% 100% 100%
9 RCC 8th Floor Slab 100% 100% 100%
10 RCC 9th Floor Slab 100% 100% 100%
11 RCC 10th Floor Slab 100% 100% 100%
12 RCC 11th Floor Slab 100% 100% 100%
13 RCC 12th Floor Slab 100% 100% 100%
14 RCC 13th Floor Slab 100% 100% 100%
15 RCC 14th Floor Slab 100% 100% 100%
16 RCC 15th Floor Slab 100% 100% 100%
17 RCC 16th Floor Slab 100% 100% 100%
18 RCC 17th Floor Slab 100% 100% 100%
19 RCC 18th Floor Slab 100% 100% 100%
20 RCC 19th Floor Slab 100% 100% 100%
21 RCC 20th Floor Slab 100% 100% 100%
22 RCC 21st Floor Slab 100% 100% 100%
23 RCC 22nd Floor Slab 100% 100% 100%
24 RCC 23rd Floor Slab 100% 100% 100%
25 Roof Slab 100% 100% 100%
26 Above Roof Slab 100% 100% 100%
27 Brickwork 100% Upto 100% 100% 100%
28 Inside Plaster 100% Upto 100% 100% 100%
29 Flooring 100% from 2nd to 6th Floor 100% 100% 100%
30 Flooring 100% from 7th to 13th Floor 100% 100% 100%
31 Flooring 100% from 14th to 15th Floor 100% 100% 100%
32 Flooring 100% from 16th to 23rd Floor 100% 100% 100%
33 DW Upto 15th Floor 100% 100% 100%
34 DW Upto 15th to 23rd Floor 100% 100% 100%
35 Plumbing (Excluding Fittings) 100% 100% 100%
36 Electrification (Excluding Fittings) 100% 100% 100%
37 IF from 2nd to 6th Floor 100% 100% 100%
38 IF from 7th to 15th Floor 100% 100% 100%
39 IF from 16th to 23rd Floor 100% 100% 100%
40 Supply & Erection of Lift 100% 100% 100%
41 Outside Plaster Upto 6th Floor 100% 100% 100%
42 Outside Plaster from 7th to 13th Floor 100% 100% 100%
43 Outside Plaster from 14th to 15th Floor 100% 100% 100%
44 Outside Plaster 100% from 16th to 23rd Floor 100% 100% 100%
45 Outside Painting 95% 95% 95%
46 Ready to Handover 95% 95% 95%